Home                     
Chief Justice           
Judges                    
Incumbency List     
Former CJs             
Former Judges       
Admin Details         
Contact Details       
Cause List              
Judgement/Orders 
Case Status     
Articles                   
Calendar                
Contact Us              

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

FIRST APPEAL No 5252 of 2001

 

For Approval and Signature:

Hon'ble MR.JUSTICE R.K.ABICHANDANI

and

Hon'ble MR.JUSTICE M.C.PATEL

============================================================

1. Whether Reporters of Local Papers may be allowed : YES

to see the judgements?

2. To be referred to the Reporter or not? : YES

3. Whether Their Lordships wish to see the fair copy : NO

of the judgement?

4. Whether this case involves a substantial question : NO

of law as to the interpretation of the Constitution

of India, 1950 of any Order made thereunder?

5. Whether it is to be circulated to the concerned : NO

Magistrate/Magistrates,Judge/Judges,Tribunal/Tribunals?

========================================================

NIRMA LTD.

Versus

LENTJES ENGERGY (INDIA) PVT. LTD

----------------------------------------------------------

Appearance:

1. First Appeal No. 5252 of 2001

MR DUSHYANT DAVE, SR. ADVOCATE WITH

MR KARTIKEY THAKAR FOR M/S TRIVEDI & GUPTA

AND MR RAMESH SINGH, Advocates

MR JP SEN FOR MR RS SANJANWALA for Respondent No. 1

MR KS NANAVATI, SR. ADVOCATE WITH MR. R.JAISINGHANI

FOR MR JAL SOLI UNWALA for Respondent No. 2

----------------------------------------------------------

CORAM : MR.JUSTICE R.K.ABICHANDANI

and

MR.JUSTICE M.C.PATEL

Date of decision: 26/07/2002

ORAL JUDGEMENT

 

(Per : MR.JUSTICE R.K.ABICHANDANI for the Court)

1. This appeal under section 37 of the Arbitration &

Conciliation Act, 1996 is directed against the order

dated 31st August 2001 made by the learned Judge, City

Civil Court No.11, Ahmedabad in Civil Miscellaneous

Application No. 21 of 2001 filed by the appellant

against these respondents under section 9 of the said

Act. By that application, the appellant sought a

direction on the respondents to preserve boilers Nos.1, 2

and 3 contracted to be supplied by them under the

agreements dated 12-12-1997, 12-12-1997 and 17-3-1998 at

the appellant's plant in Bhavnagar by conducting the

"Start-up" and "Performance Test Run" and further to

achieve the agreed parameters as per Annexure VI of the

contract dated 1-9-1997 between the appellant and the

respondent No.2 till the hearing and final disposal of

the arbitral proceedings. In the alternative, the

appellant sought a direction on the respondents to

deposit Rs.6.53 crores with the Court to be released to

the appellant so as to enable it to conduct "Start-up"

and "Performance Test Run" by engaging any other agency

as may be deemed proper by the appellant. A further

direction was sought on the respondents that, any

payments made by them to any person will be subject to

the rights and claims of the appellant for the amounts

claimed and that may be ultimately awarded by the

Arbitral Tribunal, and that the respondents should

accordingly intimate to all those whom they made such

payments. A security by way of bank guarantee was also

sought from the respondents for a sum of

Rs.60,67,18,000=00 said to have been paid by the

appellant to operate during the pendency of the arbitral

proceedings. A direction was also sought on these

respondents that they should not alienate their immovable

assets and movables except in ordinary course of business

pending the making of the award by the Arbitral Tribunal.

2. For the purpose of this appeal, the facts of the

case would be in a narrow compass. The appellant entered

into an agreement for purchase of three CFB Boilers of

100 tph each for the purpose of steam generation to be

used in the appellant's Soda Ash Plant at Bhavnagar. The

respondent No.2 had know-how in respect of such boilers

and the agreement dated 1st September 1997 was entered

into between the appellant and the respondent No.2, under

which the respondent No.2 agreed to provide to the

appellant the know-how as was required to fabricate or

get fabricated, assembled, erected and commissioned these

boilers for power generation and process steam for Soda

Ash and Pure Water for Site, as per the agreement. It

was also agreed to provide supervision of fabrication,

procurement and supply of equipments, components, spares,

consumable etc. as may be required for fabrication,

assembly, erection and commissioning of the boilers, and

to undertake that the boilers once assembled, erected and

commissioned will operate in conformity of this agreement

as well as other agreements as may be entered by

appellant with Engineer, Contractor and Erection

Contractor, which were defined in this agreement. The

terms of payment were also agreed and certain warranties

were given by the respondent No.2, which included a

guarantee (Article 7.1 (a) of the agreement), to the

effect that the Contractor, Engineer and Erection

Contractor shall duly and timely perform their respective

obligations with the appellant, as may be provided in

their respective contracts. The respondent No.2 also

guaranteed fulfillment of the warranties contained in

those contracts. In Article 7.1 (c), the respondent No.2

agreed that it would be "the principal guarantor for due

performance of the CFB boilers as covered in this

agreement and the said guarantee shall be in addition to

any guarantees which NIRMA may have from the Contractor,

Engineer and Erection Contractor". The respondent No.2

also agreed as principal guarantor to accept the

guarantee obligations as mentioned in Appendix VI of the

agreement, as also to monetarily or otherwise compensate

the appellant for all the obligations covered under

Article 7.2. It undertook to demonstrate that the boiler

was capable of operating in accordance with the technical

specifications by conducting performance test, and it was

stipulated that, in case the performance test run is not

possible due to reasons not attributable to the

respondent No.2 within seven months after provisional

acceptance of a boiler or such extended time as agreed

upon between the parties, such boiler shall be considered

as provisionally accepted and the acceptance certificate

shall be issued by the appellant. Stipulation regarding

liquidated damages was also made should the respondent

fail to fulfill its performance warrantee and the

liquidated damages were to be as specified in Annexures

to the Agreement. The agreement was to be governed

according to the laws of India as provided in Article 16.

However, by arbitration clause in Article 15.1, it was

agreed between the respondent No.2 and the appellant that

the disputes under this agreement will be finally settled

by arbitration in accordance with the Rules of

conciliation and arbitration of the International Chamber

of Commerce and the place of arbitration shall be London.

In Article 16.6, it was stipulated that the appellant

shall have no claim or demands against the respondent

No.2 other than those specified in the Agreement, and

that the liabilities of the respondent No.2 to the

appellant for all or any claim or demands of the

appellant shall be limited to what is provided in the

Agreement and shall in the aggregate limited to 15% of

the total order value that may be paid to the appellant

under the Agreement as well as 15% of the total order

value of the agreements to be entered with the Engineer,

Contractor and Erection Contractors and such limitation

shall not be alterable by decision of arbitration or

court. In Appendix VI, the performance guarantees were

enumerated and if the guarantees were not complied with

even after repairs and replacement, the appellant was

entitled to the liquidated damages at the rates which

were specifically mentioned. The appellant had a right

not to accept the unit or parts thereof in the events

enumerated in Appendix VI, which included the event where

liquidated damages exceeded 10% of the contract price.

In case of such non-acceptance, the appellant was

entitled to further use of the unit or the parts under

consideration until a suitable replacement is ready for

operation, for a period of not longer than two years

after written confirmation by the respondent No.2 of

non-acceptance and the conditions agreed upon mutually.

2.1 The respondent No.2 founded a wholly owned

subsidiary, namely the respondent No.1, which entered

into three agreements with the appellant in respect of

detailed engineering, fabrication and procurement of

components, equipments and apparatus required for the

construction of the boilers and erection and

commissioning of the boilers. The appellant had to

appoint these contractors with the approval of the

respondent No.2 and admittedly, the respondent No.1 was

appointed as Engineering, Supply and Erection Contractor

under the three agreements.

2.2 Of these three agreements, "Agreement for

Detailed Engineering" entered into on 12th December 1997

between the appellant and the respondent No.1 and which

recorded that the respondent No.2 had approved the

appointment of the respondent No.1, was for the purpose

of carrying out detailed engineering work on the basic

engineering design and know-how of the respondent No.2

required for fabrication, erection and commissioning of

the said three boilers matching with the design and

know-how of the respondent No.2. In this agreement, the

contract was defined so as to mean the agreement dated

1st September 1997 entered into between the appellant and

the respondent No.2 for supply of know-how and

supervision for three boilers. The terms of

consideration and payments were stipulated at various

stages and the final payment was to be made against their

performance bank guarantee and on completion of

performance test of the boilers, as stipulated in para

4.4.8. Warranties and indemnities were stipulated in

Article 8 and the arbitration clause was stipulated in

Article 11 to the effect that the disputes between the

respondent No.1 and the appellant, if any, shall be

referred to an arbitration in accordance with the Indian

Arbitration and Conciliation Act, 1996 for final

settlement and that the arbitration shall be conducted in

Ahmedabad (Article 11.1). In this agreement also there

was a stipulation in Article 12.4 that the appellant and

the respondent No.1 shall not mutually advance claims and

demands other than specified in the agreement, and that

the compensation and liabilities of the respondent No.2

for all damages etc. shall be limited to what was

provided in the Agreement and shall, in the aggregate,

limited to 15% of the total consideration of Rs.180 lakhs

and such limitation shall not be alterable by a decision

of an arbitrator or a court.

2.3 The Agreement for Supply was also entered into on

12th December 1997 between the respondent No.1 and the

appellant in context of the main contract between the

appellant and the respondent No.2 and it was recorded

therein that the respondent No.2 had approved the

appointment of respondent No.1 as contractor for

procurement, fabrication and supply of the equipment

required for erection and commissioning of three boilers

matching with the design and know-how of the respondent

No.2. Here again, the Contract was defined to mean the

agreement dated 1st September 1997 entered into between

the appellant and the respondent No.2 for supply of

know-how and supervision for three boilers as per the

patented design of the respondent No.2. The terms of

payment were stipulated and the final payment of 10% of

the value of the order was to be paid against Performance

Bank Guarantee and on completion of performance test of

the boilers by the respondent No.2 (as provided in the

Contract) and the Certificate issued by the appellant for

successful completion of the Performance Test for

Boilers, as stipulated in clause 3.5.9 of this Agreement.

In para 8.5, it was stipulated that, as per the contract,

parameters of the performance test were to be achieved by

the respondent No.2. If, because of defective / poor

workmanship of the material delivered by the contractor,

performance parameters are not achieved, the appellant

was free to encash the Performance Bank Guarantee to be

received from the contractor without any further

reference / recourse to the contractor, and other

suitable action as may be required to be taken by the

appellant under the contract.

2.4 The "Agreement for Erection & Commissioning" was

executed on 17th March 1998 between the appellant and the

respondent No.1 after it was approved by the respondent

No.2, for carrying out erection and commissioning of

three CFB Boilers of 100 tph each matching with the

design and know-how of the respondent No.2 as well as

detailed engineering and supplies as may be done by the

respondent No.1 (Clause (e) of the Preamble). Under this

Agreement, the respondent No.1 undertook and agreed that

the services to be rendered by it constituted "the total

services required for the Erection testing of the Plant"

(Article 2.5). The obligation of the appellant

enumerated in Article 3.1 included providing electricity

at one point free of cost, and providing open and

levelled area for fabrication. The terms of payment were

stipulated and as per Article 4.4.4, final payment being

10% of consideration was to be paid against Performance

Bank Guarantee and on completion of performance test and

Certificate issued by NIRMA for the successful completion

of the performance test for boilers. Specimen of

performance guarantee is annexed at Annexure 3 to this

agreement. Stipulations regarding Mechanical Completion

Test after the erection of the Plant was completed,

Start-Up and Performance Test Run were made in Articles

7.10, 7.11 and 7.12. If the guaranteed performance was

achieved and a certificate was issued to that effect by

the appellant (Performance Acceptance Certificate), the

respondent No.1 would stand discharged from the

contractual obligations in respect of the boiler for

which the certificate is issued (Article 7.12.2).

Stipulation identical to the one contained in the other

agreements by which the aggregate limit of liabilities

was fixed to 15% of the total consideration was also

adopted in this agreement in Article 11.4. In the

arbitration clause in Article 10, it is provided that the

arbitration shall be conducted in Ahmedabad.

3. It will be seen from the nature of the aforesaid

four agreements that the respondent No.2 had a know-how

in respect of the boilers having patented design, and

that it had undertaken to give that know-how to the

appellant through the contractors of its choice, with

whom the appellant entered into agreements after due

approval from the respondent No.2. The common element in

all the four agreements was that the performance test run

of the boilers was to be conducted and the final payment

of 10% was to be made against the performance guarantee

and a successful performance test. The respondent No.2

had undertaken to carry out the obligations of the

respondent No.1 under the three agreements. The

arbitration clause in the agreement with the respondent

No.2 named London as the place for arbitration, while in

the three agreements executed by the respondent No.1, the

seat of arbitration was Ahmedabad.

4. The dispute arose between the parties leading to

a reference being made before the Arbitral Tribunal at

Ahmedabad in respect of the three arbitration agreements

entered between the appellant and the respondent No.1 and

a reference made to the Arbitral Tribunal of the

International Court of Commerce, at London in respect of

the main agreement which is described as the Contract in

the other agreements, between the appellant and the

respondent No.2.

5. In the Statement of Claim dated 12-11-2000 made

by the appellant before the Arbitral Tribunal at

Ahmedabad (a copy of which is at Volume III of the Paper

Book of the appellant, at Annexure "ZE" at page 255 to

297), the appellant - claimant prayed for a declaration

that the respondent No.1 had failed to perform its

obligations under the said three agreements, and that the

claimant was entitled to be re-paid Rs.60,67,18,000=00

paid to the respondent No.1 under these agreements on

account of its failure to perform its obligations

together with interest at 18% per annum from the date of

payment till realisation of the amount. In the

alternative, it was prayed that the claimant be awarded a

sum of Rs.8,20,50,000=00 which according to the appellant

was paid in excess to the respondent No.1 together with

interest at 18% per annum. A further sum of

Rs.66,08,32,000=00 was claimed as the amount of "idle

charges" on account of idle charges of labour, fixed

cost, interest charges etc. for the period between

1-9-1999 till 29-2-2000, as stated in paragraph 68(3) of

the statement. Other sums of Rs.33,47,14,000=00 (on

account of compensation for loss and damage caused by

diverse breaches of contract), Rs.14,65,84,000=00 (on

account of insufficient boiler operation),

Rs.2,06,80,000=00 (on account of use of an incorrect

primer, namely, red oxide primer instead of zinc silicate

primer), Rs.1,60,05,000=00 (towards reimbursement of

material costs), Rs.2,95,14,000=00 (towards reimbursement

of services carried on behalf of the respondent No.1) and

Rs.1,29,19,000=00 were claimed under various heads

enumerated in the claims put up in paragraph 68 of the

statement.

5.1 On the disputes arising between the parties, the

appellant invoked the arbitration clause under each of

the three agreements by issuing notice dated 29-7-2001

(Annexure "ZB") to the respondent No.1. The respondent

No.1 refuted the claim made by the appellant by its

letter (at Annexure "ZC"). On invocation of the

arbitration clause, the Arbitral Tribunal was constituted

and it entered upon the reference on 8-10-2000. The

petitioner filed statement of claim and the respondents

filed the written statement as per the directions of the

Tribunal. Thereafter, the petitioner filed the

application under section 9 of the said Act on 9th

January 2001 for the reliefs referred to earlier.

6. The learned City Civil Judge noted that, though

the Arbitral Tribunal had entered upon reference on

8-10-2000, the application under section 9 was made on

9-1-2001 and no interim relief was at any point of time

sought from the Arbitral Tribunal. It was held that

there was no concrete reason placed on record to point

out as to what were the reasonable grounds requiring the

court to exercise its powers for grant of interim

measures, especially in view of the fact that both the

sides have made allegations and counter allegations

before the Arbitral Tribunal as well as the before the

ICC, London. The trial Court observed that the issues

regarding obligation to conduct "Start Up and Performance

Test" in respect of these boilers were pending before the

Arbitral Tribunal and the Court was not required to go

into the merits of those disputes. Dealing with the

contention that the Arbitral Tribunal did not enjoy wide

powers of a court for granting interim measures, the

court observed that it was not pointed out as to how the

powers of Arbitral Tribunal under the Act were limited.

It held that this submission was not acceptable in

absence of any cogent reason for not moving the Arbitral

Tribunal for any interim measure under section 17 of the

Act. The Court held that there was absolutely no

question of the maintainability of the application,

because, that aspect was decided in M/s Sundaram Finance

Ltd. v. M/s NEPC India Ltd., reported in JT 1999 (1) SC

49, in which it was held that the Court was empowered to

pass interim order before or during the arbitral

proceedings under section 9 of the Act. After holding

that the Court had the power, under section 9 of the Act,

to issue orders of interim measures, it was held that

there was no justification in the appellant not moving

the Arbitral Tribunal for getting interim measures, and

therefore, it was not desirable to intervene and grant

the interim relief.

6.1 On merits, it was held that, prima facie, in view

of the annual report of the appellant regarding the

completion of the commissioning of the boilers and the

same being fully operational, there did not appear to be

any defect or failures to have come on the record and all

the suppositions or the possibilities of failures

attempted to be the basis for getting the relief of

specific performance appeared to be hypothetical

apprehensions. It was held that the Arbitral Tribunal

was going to decide as to whether the boilers supplied

were defective, and whether the appellant had prevented

the respondent from fulfilling its part of the contract.

It was noted that the Arbitral Tribunal was also required

to decide whether the respondent No.1 proved that the

boilers suffered damage after installation due to their

being operated by the appellant, or whether the appellant

was guilty of delay. The Court found that the appellant

had not made out any prima facie case, and that the

issues urged before the Court could not be decided by it

at prima facie stage for granting interim measures like

specific performance or attachment sought by the

appellant. The Court also held that the appellant itself

had quantified the compensation in terms of damages and

therefore, no question arose for granting injunction. It

was further held that the directions in form of specific

performance would tantamount to the Court concluding,

before the Arbitral Tribunal arbitrates, upon the facts

in issue before it. Referring to the ratio of the

decision of the Apex Court in Colgate Palmolive (India)

Ltd. reported in (1999) 7 SCC 1, it was held that the

appellant was not entitled to any interim relief on the

basis of any of the criteria set out in the said

decision. It was noted that there was a strong ground

operating in favour of the respondent No.1, having

relevance on the aspect of balance of convenience, that

the three boilers were in fact erected and commissioned

and the completion of the project was shown in the annual

report of Company ending on 31st March 2000, which stated

that the project was completed ahead of time for the

amount which was less than the stipulated amount and that

self-sufficiency in generating steam for the Soda Ash

plant of the appellant was achieved. It was also noted

that the appellant had invoked the bank guarantee given

by the respondent No.1 and that there was also a

counter-claim of the respondent to make good the

outstanding dues being part of the consideration of the

three agreements. It was also observed that there was no

existing pecuniary liability, making it obligatory for

the respondents to furnish a guarantee, and that the

relief of recovery of damages in contract was not a debt

or any outstanding pecuniary liability. Referring to the

provisions of sections 40 and 41 of the Specific Relief

Act, the Court held that it cannot grant injunction in a

case where the non-performance can be duly compensated.

It was held that the grant of interim relief prayed for

by the appellant may amount to granting of specific

performance of the contract which was not permissible in

view of the damages sought for by the appellant. On the

basis of the ratio of the decision of the Supreme Court

in Cotton Corporation of India Ltd. v. United

Industrial Bank Ltd., reported in AIR 1983 SC 1272, it

was held that since no final relief in terms of specific

performance was available, temporary relief of the same

nature cannot be availed of by the appellant. Referring

to the Commentaries on Russell on arbitration and Dr.

Peter Binder, which were cited before it, the Court held

that; " Even if interim measures against the parties not

involved in arbitration can be enforced through legal

judicial system as commented by Dr. Peter Binder and

relied upon by the petitioner, no cause is made out to do

so, in light of the facts and circumstances in the

matter". It was held that though the Court had

jurisdiction under Section 9 to grant interim measures,

there was no case made out either for the mandatory

relief or for any other interim measure to enable to the

petitioner to get the relief claimed and that there was

no evidence to hold, prima facie, that the respondents

were stripping itself of its assets so as to warrant

grant of Mareva injunction. The Court, thus, by its

detailed order, rejected the application for interim

measures under section 9 of the Act.

7. The learned Senior Counsel for the appellant

argued that the approach of the trial Court that the

Court should not exercise its jurisdiction under section

9 of the said Act when the appellant can move the

Arbitral tribunal for interim measures under section 17

of the Act, was erroneous and not warranted by the

provisions of the said Act and the decisions of the Apex

Court. It was further contended that the Court can issue

orders under section 9 of the Act even against a third

party and therefore, the fact that the respondent No.2 as

on today is struck off as a party from the arbitral

proceedings on the ground that he had not agreed to the

arbitral clause contained in the three agreements which

were entered into between the appellant and the

respondent No.1, the Court can still issue interim orders

binding the respondent No.2 to preserve the outcome of

the arbitral proceedings. The learned counsel argued

that "Start Up" and "Performance Test Run" were the

stipulations which were essential part of the contract

with the respondent No.2 and the three other agreements

entered with the respondent No.1 at the behest of the

respondent No.2 by the appellant. It was submitted that

unless the parameters stipulated in the contract were

achieved, by a positive performance test run, even the

risk did not pass to the appellant. It was submitted

that it was essential to order by way of interim measure

that the performance test run should be conducted by the

respondent No.2, who had undertaken to demonstrate the

performance of the boilers under the agreement, with a

view to enable the appellant to decide finally whether to

reject the boilers or not, and therefore, such an interim

measure cannot be said to be for enforcing any relief of

specific performance of the contract. It was submitted

that, having regard to the nature of the claim before the

Arbitral Tribunal made by the appellant, it was essential

to insist upon such performance test run to be conducted

by the respondents in aid of the outcome of the arbitral

proceedings and therefore, the prayer of the appellant

for such an interim measure cannot be brushed aside on a

plea that interim specific performance cannot be ordered

when it is not finally prayed for. It was submitted that

this essential step of conducting the performance test

run could be insisted upon even on equitable grounds

having regard to the large investment made by the

appellant under these contracts with a view to acquire

three boilers which were supposed to achieve certain

parameters which could be ascertained only by conducting

the performance test run. It was argued that, even if

the respondent No.2 was to be treated as a third party to

the arbitral proceedings, the Court was empowered to

grant an interim relief under section 9 of the Act. It

was argued that, under section 9 of the Act, the Court

was empowered to make orders in the same manner "as it

has for the purpose of, and in relation to, any

proceedings before it", and that the rationale for the

Court being so empowered was that the power of

enforcement did not vest with the Arbitral Tribunal and

that the Court could make orders even against third

parties. It was submitted that the power under section 9

was required to be exercised by applying well accepted

principles governing grant of injunction or interim

relief, and such power should be exercised in connection

with preservation of goods, their inspection or

experimentation which would have relevance on the

questions that may arise during the arbitral proceedings.

It was submitted that the relief prayed for in the

Statement of Claim before the Arbitral Tribunal and in

the Counter-claim as well as the issues framed by the

Tribunal would clearly encompass the prayers made in the

application of the appellant under section 9 of the Act.

It was also argued that the mandatory relief could be

granted where the appellant has a strong case for trial

and with a view to prevent irreparable or serious injury

which cannot be compensated in terms of money. It was

submitted that the trial Court had overlooked the scope

of section 9 of the said Act and the provisions of

sections 23 and 40 of the Specific Relief Act, 1963 in

context of which the appellant was entitled to claim the

interim relief. It was also argued that the Court below

failed to appreciate that there were three multiple

boiler agreements containing entire contractual

obligations and it did not appreciate the commercial

uniqueness of the transaction, that such three boilers

could not be readily obtained from the open market by the

appellant.

7.1 In support of his contentions, the learned Senior

Counsel relied upon the following extracts from the

textbooks, and, the precedents.

[a] From Chitty on Contract (28th Edition), the

learned Senior Counsel referred to paragraph

37-106, which reads thus :

"Performance Obligations : Contracts for

the provision of process plant and

machinery are divided into an initial

construction period, followed by a post

completion period during which the plant

must be operated and performance

demonstrated. The provisions as to

testing are usually accompanied by a

detailed protocol involving stages, such

as an initial period of operation

followed by performance tests over a

prescribed period. The contract may

provided prescribed penalties or

deductions as compensation in respect of

failure to meet required performance.

The detailed performance requirements

will be specific to each item of plant or

machinery, but standard forms exist which

prescribe the basic contract structure.

In addition to performance of

obligations, the contract may require

other services, such as training of

operating personnel, the provision of

spares for the plant, and detailed

operating manuals and instructions."

[b] From Dr. Peter Binder's International Commercial

Arbitration In UNCITRAL Model Law Jurisdictions

(First Edition 2000 Published by Sweet &

Maxwell), the following observations in para

2.056 were referred to;

"Conclusion : In certain circumstances,

especially where the arbitral tribunal

has not yet been established, the

issuance of interim measures by the court

is the only way assets can be saved for a

future arbitration. Otherwise, the

claimant could end up with a worthless

arbitral award due to the fact that the

loosing party has moved his attachable

assets to a "safe" jurisdiction where

they are out of reach of the claimant's

seizure. The importance of such a

provision in an arbitration law is

therefore evident, and a comparison of

the adopting jurisdictions shows that all

jurisdictions include some kind of

provision on the issue, all granting the

parties permission to seek court ordered

interim measures."

[c] From Russel on Arbitration (21st Edition),

reliance was placed on the following

observations;

[d] Interim orders

"5-095 Types and purposes of interim

orders :

Consideration should also be given at a

preliminary stage to whether interim

orders should be made. The term "interim

orders" is not issued in the 1996 Act, is

adopted here to refer to orders or

directions on such matters as security

for court's, interim preservation orders

and injunctions. These orders are often

designed to protect the position of the

parties and / or preserve the status quo

pending the outcome of the reference.

However, they may also be examples of the

tribunal exercising its procedural powers

in relation to evidential matters."

"5-096 From whom to seek interim orders

- The parties are free to agree what

powers the tribunal is to have with

regard to interim orders, but unless the

parties have agreed otherwise in writing

then the tribunal has the powers set out

in sections 38(3) to (6) of the

Arbitration Act, 1996. Interim orders

may also be sought from the court, but in

the ordinary course the parties would be

expected to apply to the tribunal in

those cases where the tribunal has the

power to make them. Applications to

court will also be appropriate where for

example the order is sought against a

third party over whom the tribunal has no

jurisdiction, or where any order by the

tribunal is likely to be ineffective."

"5-099 Preservation of property Section

- Section 38(4) of the Arbitration Act

1996 provides that the tribunal may give

directions in relation to property

subject to two provisos. First, the

property must be the subject-matter of

the reference or property as to which a

question arises in the proceedings.

Secondly, the property must be owned by

or in the possession of a party to the

proceedings. This reflects the

tribunal's inability to enforce its

orders against third parties. Relief may

be sought from the court if the provisos

are not met or for some other reason the

tribunal is unable to act or to act

effectively."

"6.132 Third parties : Further, a

tribunal does not have jurisdiction over

a third party, even though the third

party may hold the money, goods or

property in dispute. The tribunal is

therefore even less able to secure

compliance by a third party with an

injunction it may grant than it is to

secure compliance by the parties to the

arbitration."

[d] Excerpts from The Law and Practice of Commercial

Arbitration in England (Second Edition) Sir

Michael J. Mustill & Stewart C. Boyd, which was

relied upon from pages 330 are re-produced

hereunder :

"An injunction is a powerful weapon,

since it is backed by the powers of the

Court of Equity to act in personam and

these include, in the last resort, orders

for the committal of a recalcitrant

defendant, or that attachment of his

property. In the context of an

arbitration, an interlocutory injunction

will usually fulfill one or other of two

functions. First, to protect the

property in issue from abuse by one of

the parties : for example, to prohibit

the removal of property from the United

Kingdom, the object being to ensure that

any order which the arbitrator may

ultimately make as to the disposition of

the property will not be rendered

academic by the previous removal of the

property. Second, to bring about a kind

of interim specific performance of the

contract. For example, if the issue is

whether a charterparty has been validly

terminated by the respondent, the court

may issue an injunction prohibiting the

respondent from employing the vessel

otherwise than in accordance with the

charter : thus, in many cases, forcing

him to keep the vessel in the service of

the charterer pending the resolution of

the dispute.

The Court has power to grant an

interlocutory injunction in respect of

matters which are the subject of an

arbitration. The making of an

interlocutory injunction, or the pendency

of an application for such an injunction,

does not prevent the court from granting

a stay of any action which is brought in

respect of the substantive dispute, the

only purpose of the injunction being to

maintain the status quo pending the

award. In general, the exercise of the

discretion where there is a pending

arbitration is likely to proceed on the

same principles as in relation to an

action in the High Court."

From the same book, the following excerpt was

also referred which is at page 332 :

"(iv) Securing the sum in dispute :

Where the right of a party to a specific

fund is in dispute in a reference, the

court has power to order the fund to be

paid into court or otherwise secured.

The forms of security most likely to be

ordered are the provision of a bank

guarantee or the payment of the fund into

a bank account in the joint names of the

parties or their advisors. It is

probable that the court alone, and not

the arbitrator, has power to make such an

order.

It will be noted that this power does not

enable a party to recover sums on account

of damages in advance of the hearing,

even if liability is undisputed and it is

clear that some monetary award will be

met. The power exists only where an

identified fund is in dispute - as where,

for example, it is alleged that the

respondent is trustee for the claimant in

respect of a specific sum of money."

[e] The decision of the Supreme Court in case of

Sundaram Finance Ltd. v. NEPC India Ltd.,

reported in (1999) 2 SCC 479 was cited for the

proposition that though section 17 gives the

Arbitral Tribunal the power to pass orders, the

same cannot be enforced as orders of a court, and

that it is for this reason that section 9

admittedly gives the court power to pass interim

orders during the arbitration proceedings. It

was held that interim orders can be passed by the

Court under section 9 before or during the

arbitral proceedings, and that, reading the

section as a whole, it appears that the court has

jurisdiction to entertain an application under

section 9 either before arbitral proceedings or

during arbitral proceedings or after the making

of the arbitral award but before it is enforced

in accordance with section 36 of the Act. The

Court approved the observations in Russel on

Arbitration that power to grant an interim

injunction extends to granting of a Mareva

injunction in appropriate cases although the

court will be slow to grant an injunction which

provides a remedy of essentially the same kind as

is ultimately being sought from the Arbitral

Tribunal.

[f] Reliance was placed on the decision of the

Supreme Court in Bhatia International v. Bulk

Trading S.A. and another, reported in (2002) 4

SCC 105 for the proposition that an application

for interim measure can be made to the Courts in

India whether the arbitration takes place in

India before or during the arbitral proceedings.

[g] The decision of the Madhya Pradesh High Court in

case of Nepa Ltd. v. Manoj Kumar Agrawal,

reported in AIR 1999 MP 57 was cited for the

proposition that the provisions of section 9

empower the Civil Court to take interim measures

for preservation and safe custody of the subject

matter in arbitration agreement and for that

purpose, to issue interim injunction. Existence

of an arbitration clause and the necessity of

taking interim measures alone are required to be

considered for issuing necessary directions or

orders. ( See para 17 of the judgement).

[h] The decision of the Supreme Court in case of

Colgate Palmolive (India) Ltd. v. Hindustan

Lever Ltd., reported in (1999) 7 SCC 1 was

referred to point out the considerations which

ought to weigh with the Court hearing an

application for grant of injunction which are

setout in paragraph 4 of the judgement. On the

basis of these considerations, it was argued that

the Court, while dealing with the matter, ought

not to ignore the factum of strength of one

party's case being stronger than the other, and

that the issue is to be looked at from the point

of view as to whether on refusal of the

injunction the plaintiff would suffer irreparable

loss and injury keeping in view the strength of

the party's case.

[i] The decision of the Delhi High Court in case of

Satish Aggarwal v. Subhash Chand Aggarwal,

reported in 2000 (55) DRJ was cited to point out

that, in an application under section 9 for

interim measures, an interim order in terms of

section 37 of the Partnership Act was made.

Reference was made to the decision of the Delhi

High Court in case of Kanshi Ram v. Punjab

National Bank, reported in 2000 (55) DRJ, for the

proposition that in absence of guidelines as to

grant of relief under section 9Iii)(b) of the

Act, the Court has to apply the provisions of

Order 38 Rule 5 of the Code of Civil Procedure.

[j] A decision of the Bombay High Court in case of

Newage Fincorp (India) Ltd. v. Asia Corp.

Securities Ltd., reported in 2000 (3) Arbitration

Law Reporters 687 (Bombay) was cited for the

proposition contained in paragraph 35 of the

judgement that, in granting or refusing to grant

interim measures, the Court has wide discretion

under section 9 of the Act. In that case, the

Court found that it was necessary to preserve the

subject matter of arbitral dispute by granting

interim measures in aid of final reliefs to which

the petitioners may be entitled in the

arbitration proceedings and the respondents were

restrained from transferring the membership card

of the Stock Exchange.

[k] The decision of the Delhi High Court in case of

MMTC Ltd. v. Shyam Singh Chaudhary, reported in

2001 (57) DRJ 743 was cited in support of the

argument that, all the deeds between the

appellant and the respondents were intrinsically

and integrally intertwined, and therefore, the

question of territoriality should be view from

the angle that the dispute may also arise within

the jurisdiction of the Arbitral Tribunal in

Ahmedabad even if it could arise under the

arbitral clause 15 of the agreement with the

respondent No.2 before the ICC - London.

[n] The decision of the Madhya Pradesh High Court in

case of Jabalpur Cable Network Pvt. Ltd. v.

E.S.P.N. Software India Pvt. Ltd., reported in

AIR 1999 MP 271 was cited to point out that, in

respect of the articles which were of special

value and the goods which were not easily

obtainable in the market, it could be presumed

that the breach of contract to transfer the goods

cannot be relieved by payment of money in lieu

thereof. It was held that it would be most

inequitable not to grant relief to the appellant

to transmit information which is of great value

when it is live and looses its importance after

the telecast is over.

[o] The decision of the Supreme Court in case of

Dorab Cawasji Warden v. Coomi Sorab Warden,

reported in AIR 1990 SC 867 was heavily relied

upon for the proposition that the relief of

interlocutory mandatory injunction would be

granted generally to preserve or restore the

status quo. The Supreme Court held that, being

essentially an equitable relief, the grant or

refusal of an interlocutory mandatory injunction

shall ultimately rest in the sound judicial

discretion of the Court to be exercised in the

light of the facts and circumstances of each

case.

[p] The decision of the Rangoon High Court in case of

L. Dawson v. Princess Rounac Zamani Begum,

reported in AIR 1928 Rangoon 268 was cited for

the proposition that a wrong doer cannot insist

the person wronged to accept compensation in lieu

of injunction, and that mandatory injunction is

ordinarily granted unless the injury is small and

capable of being compensated by small money

payment.

[q] The decision of the Madras High Court in case of

Veeramalai Chettiar v. Ramayee Ammal, reported

in AIR 1962 MADRAS 437 was cited for the view

that the provisions of the Civil Procedure Code

will generally apply to the arbitration

proceedings.

[r] The decision of the Delhi High Court in case of

Olex Focas Pty. Ltd. v. Skodaexport Co. Ltd.,

reported in 1999 (Supp) Arbitration Law Reported

533 (Delhi) was cited to point out that the Court

held in paragraph 64 of its judgement that,

according to the provisions of the said Act, the

Courts are vested with the jurisdiction and power

to grant interim relief in appropriate cases, and

that the court's power to grant interim relief

would even strengthen the arbitration

proceedings, otherwise, in some cases, the award

may in fact be reduced to only a paper award.

[s] The decision of the Delhi High Court in case of

Niko Resources Ltd. v. Union of India, reported

in 2001(3) Arb. L.R. 196 (Delhi) (DB) was cited

to point out from paragraph 28 of the judgement

that it was held that, if it becomes necessary to

protect the interests of any party and any

interim measures of protection are required,

appropriate directions can always be issued to

the respondent to ensure the protection for the

benefit of the appellant even though the measures

may have an implication on GSPL, which was not a

party before the Court.

[t] The decision of the Delhi High Court in case of

CREF Finance Ltd. v. Puri Construction Ltd. &

ors., reported in 2000(3) Arb. L.R. 331 (Delhi)

was relied upon for the proposition contained in

paragraph 10 of its judgement that the Court had

jurisdiction to pass orders under Section 9,

until the award was submitted for enforcement

under section 36 of the Act.

8. The learned counsel appearing for the respondent

No.1 contended that the appellant had issued mechanical

completion and provisional acceptance certificates in

respect of all the three boilers and thereafter, they are

being used by the appellant for its Soda Ash Plant. It

was argued that the performance test run was rendered

redundant by the conduct of the appellant. We were taken

through the pleadings in detail to point out the grounds

on which, according to the respondent No.1, the

performance test run became redundant. It was further

argued that the bank guarantee of Rs.13 crores was

invoked by the appellant, as against the "non-conduct" of

the performance test run, on 28-7-2000, and that even

though all the three boilers were commissioned and are

being used by the appellant, 25% of the total

consideration is yet to be paid by the appellant to the

respondents. It was submitted that, as per the clauses

contained in all the three agreements, maximum liability

of the respondent No.1 on any count was limited to 15% of

the contracted value, as liquidating damages. It was

also argued that no specific performance was sought in

the arbitral proceedings and therefore, it could not be

granted in the application for interim relief. It was

further argued that no injunction could be issued where

damages would be an adequate remedy. It was contended

that the appellant was in possession of the boilers and

it could not keep the boilers and claim the refund as

well, of the price of these boilers which were not

rejected by the appellant. It was submitted that the

claim for damages made by the appellant was yet to be

decided in the arbitration proceedings and since no

liability for money was outstanding, there was no case

made out for ordering any security deposit in favour of

the appellant.

8.1 The learned Senior Counsel appearing for the

respondent No.2 adopted these contentions and further

argued that the respondent No.2 was not a party to the

arbitration proceedings in Ahmedabad, and that it was not

a party to any of the three agreements entered into

between the appellant and the respondent No.1, and that

no interim orders could be made against the respondent

No.2, especially in view of the fact that the parties to

the Contract i.e. the appellant and the respondent No.2

had chosen the place of arbitration to be London as per

Article 16 of their agreement, which arbitration

proceeding was in fact pending before the International

Court of Arbitration, ICC - London. It was further

argued that the Arbitral Tribunal, at Ahmedabad, had

already made orders dated 17-2-2001 and 4-3-2001 that it

had no jurisdiction to entertain and decide any dispute

between the appellant and the respondent No.2. That

order of the Tribunal dated 7-2-2001 was confirmed by the

City Civil Court by its order dated 31-8-2001 and a

Revision Application being No. 123 of 2002 was filed on

6-2-2002, which is pending in the High Court. Therefore,

as on today, the respondent No.2 was not even a party in

the arbitral proceedings though initially impleaded. It

was submitted that the Court could grant interim relief

under section 9 of the said Act only against the parties

to the arbitration proceedings and therefore, the

respondent No.2 cannot be made liable by any interim

relief to conduct any performance test or to furnish any

security for the claim made by the appellant. It was

also pointed out that the appellant had initially made a

counter-claim before the Arbitral Tribunal at London,

which was withdrawn. It was submitted that, any interim

direction given against the respondent No.2 would amount

to enforcing the liability of the respondent No.2 under

the agreement between it and the appellant, the disputes

under which were required to be arbitrated upon by the

ICC - London. It was also contended that the guarantee

contained in the know-how agreement was no longer valid

and / or enforceable, and that the guarantee was in

respect of performance and not in respect of any

pecuniary or other liability of respondent No.1. Since

the parties to the know-how agreement had consciously

chosen the forum of ICC, London for settling their

disputes, the appellant cannot resile from that agreement

by praying for reliefs in any other forum. It was argued

that the liability of the guarantor was a separate and

distinct from that of the principal debtor, and that the

application for interim relief was wholly unconnected

with the know-how agreement between the appellant and the

respondent No.2. It was also argued that the respondent

No.2 as a holding company cannot be made liable for any

liabilities of its wholly owned subsidiary, the

respondent No.1 and no interim relief could be granted in

favour of the appellant on that ground. Both the learned

counsel for the respondents supported the reasoning of

the trial Judge.

8.2 In support of their contentions, the learned

counsel for the respondents have referred to the

following decisions :

[a] The decision of the Supreme Court in case of

Fateh Chand v. Balkishan Dass, reported in AIR

1963 SC 1405 was cited for the proposition that a

claim for liquidated damages would not lie unless

the plaintiff proves loss or legal injury.

[b] The decision of the Supreme Court in case of

Cotton Corporation of India Ltd. v. United

Industrial Bank Ltd., reported in AIR 1983 SC

1272 and a decision of this Court in case of

Gujarat Electricity Board v. Maheshkumar & Co.,

reported in AIR 1982 Gujarat 289, were cited for

the proposition that interim relief can be

granted only in aid of the final relief.

[c] The decision of the Privy Council in Ardeshir H.

Mama v. Flora Sasoon, reported in AIR 1928 P.C.

208, the decision of the Kerala High Court in

Ayissabi v. Gopala Konar, reported in AIR 1989

KER 134 and the Madras High Court decision in

K.S.Sundaramayyar v. K. Jagadeesan, reported in

AIR 1985 MADRAS 85 were referred to for the

proposition that once a party makes a claim for

damages, he treats the contract as repudiated and

thereafter, cannot seek a specific performance of

a contract.

[d] The decision of the Allahabad High Court in Kashi

Nath v. Municipal Board, reported in AIR 1989

ALh. 375 was cited for the propsition that the

Court will not be justified in granting mandatory

relief by which it is required that a party

should undertake works of considerable extent by

way of improvements and constructions requiring a

good deal of engineering skill besides

considerable amount of money to meet the expense,

because, the Court is not capable of supervising

the works and thus, enforcing the injunction and

because award of damages is certainly an

efficacious remedy in such a case.

[e] The decision of the Delhi High Court in case of

M/s Magnum Films v. Golcha Properties Pvt.

Ltd., reported in AIR 1983 DELHI 392 was cited

for the proposition that the temporary mandatory

injunction can be issued only in case of extreme

hardship and compelling circumstances and mostly

in those cases when status quo existing on the

date of the institution of the suit is to be

restored. For this proposition, reliance was

also placed on the decision of the Calcutta High

Court in Nandan Pictures Ltd. v. Art Pictures

Ltd., reported in AIR 1956 CAL. 428.

[f] The decision of the Delhi High Court in M/s

Global Company Ltd. v. National Fertilizers

Ltd., reported in AIR 1998 DELHI 397 was cited

for the proposition that the principles of Order

39 Rule 5 of the CPC in respect of attachment and

Order 39 of the CPC in respect of injunctions

would apply to applications under section 9 of

the Arbitration act.

[g] The decision in Union of India v. Raman Iron

Foundry, reported in 1974 (2) SCC 231 was cited

for the proposition that a claim for damages is

not a liquidated sum.

[h] The decision of the Supreme Court in Colgate

Palmolive (India) Ltd. v. Hindustan Lever Ltd.,

reported in (1999) 7 SCC 1 was relied upon for

the proposition that, in deciding whether an

injunction should be issued, the Court should

determine whether one party's case is stronger

than the other.

9. The trial Court has observed that there was no

satisfactory explanation coming forth from the appellant

as to why it did not first approach the Arbitration

Tribunal under section 17 of the Act before invoking the

Court's discretion to order interim measures under

section 9 of the said Act. Sections 9 and 17 of the Act

which fall for our consideration are re-produced

hereunder:-

"Section - 9 - Interim Measures etc. by Court A

party may, before or during arbitral proceedings

or at any time after the making of the arbitral

award but before it is enforced in accordance

with section 36, apply to a Court -

(i) for the appointment of a guardian for a

minor or a person of unsound mind for the

purposes of arbitral proceedings; or

(ii) for an interim measure of protection in

respect of any of the following matters,

namely :

(a) the preservation, interim custody

or sale of any goods which are

the subject matter of the

arbitration agreement;

(b) securing the amount in dispute in

the arbitration;

(c) the detention, preservation or

inspection of any property or

thing which is the subject matter

of the dispute in arbitration, or

as to which any question may

arise therein and authorizing for

any of the aforesaid purposes any

person to enter upon any land or

building in the possession of any

party, or authorizing any samples

to be taken or any observation to

be made, or experiment to be

tried, which may be necessary or

expedient for the purpose of

obtaining full information or

evidence;

(d) interim injunction or the

appointment of a receiver;

(e) such other interim measure of

protection as may appear to the

Court to be just and convenient,

and the Court shall have the same power for

making orders as it has for the purpose of, and

in relation to, any proceedings before it.

Section - 17 - Interim Measures ordered by

Arbitral Tribunal-

(1) Unless otherwise agreed by the parties,

the arbitral tribunal may, at the request

of a party, order a party to take any

interim measure of protection as the

arbitral tribunal may consider necessary

in respect of the subject matter of the

dispute.

(2) The arbitral tribunal may require a party

to provide appropriate security in

connection with a measure ordered under

sub-section (1)."

9. The expression "Arbitral award" includes an

interim award under section 2(1)(c) of the Act, unless

the context otherwise requires. The Arbitral Tribunal

may, at any time during the arbitral proceedings, make an

interim arbitral award on any matter with respect to

which it may make a final arbitral award, as provided by

section 31(6) of the Act. The Arbitral Tribunal, at the

request of a party, order a party under Section 17 of the

Act to take any interim measure of protection as the

arbitral tribunal may consider necessary in respect of

the subject matter of the dispute, unless otherwise

agreed to by the parties. The provisions of section 17

are identically worded as Article 17 of the UNCITRAL

Model Law.

9.1 Article 26(1) of the UNCITRAL Arbitration Rules,

1976 was a provision similar to the provisions of Article

17 of the Model Law enabling the Arbitral Tribunal to

take any interim measures including measures of

conservation of goods forming the subject matter of the

dispute. Article 26(2) of the Rules of 1976 provided

that such interim measures may be established in the form

of an interim award. Under the said Act, however, an

appeal lies under section 37(1) against the order of

interim measure made under section 17 of the Act. It is,

however, clear that even if the Arbitral Tribunal grants

interim injunction, it cannot be enforced without resort

to the Court. If an Arbitral Tribunal had the power to

effectively order measures of interim relief that the

Court can provide, there would hardly be any need to

provide for court applications for interim measures.

Since the Arbitral Tribunal's jurisdiction is limited,

the assistance of Court is required.

9.2 The basic limitation on the power of the Arbitral

Tribunal lies in the arbitration agreement which binds

only the parties to the agreement. Arbitration clause

cannot bind anyone who is not a party to it. Thus, the

Arbitral Tribunal will have no power to issue interim

orders which can bind third parties over whom it has no

consensual jurisdiction. Moreover, Arbitral Tribunals

have no coercive power to enforce their orders. An

injunction ordered by Arbitral Tribunal would not be

fortified with the threat of contempt of court, but would

only have contractual effect between the parties. It is

therefore evident that access to the court under section

9 of the said Act for certain kinds of interim relief in

arbitration cases, would not only be expedient but

necessary as a provisional remedy to ensure that a just

outcome of the arbitral proceedings does not get defeated

and the Arbitral Tribunal can effectively resolve the

disputes. The range of interim measures that can be

issued under section 9 of the said Act is considerably

wider than that under section 17. The provisions of

sections 9 and 17 modelled on the UNCITRAL Model Law on

International Commercial Arbitration (1985) give an

option of free access to both the court and the arbitral

tribunal for interim relief and give the parties a choice

between Arbitral Tribunal or Court for interim reliefs.

Furthermore, a party to an arbitration agreement could

approach the Court for interim protection measures under

section 9 before or during the arbitration proceedings,

which indicates that the efficacy of court's power to

grant interim relief remains the same even during the

arbitration proceedings. It would therefore not be

proper to relegate a party who approaches the court for

interim relief under section 9, to the Arbitral Tribunal

for an interim measure of protection under section 17.

The view that the Court should not exercise its

discretionary powers under section 9 when a party to the

arbitration agreement can move the Arbitral Tribunal

under section 17 cannot, therefore, be accepted.

10. The contention on behalf of the respondent No.2

that the Court cannot consider the agreement between the

appellant and the respondent No.2, because, that would

amount to enforcing liability of the respondent No.2

which can be done only by the ICC - London, is

misconceived. When the Arbitral Tribunal has

jurisdiction only to decide disputes arising under one

set of contracts, it does not preclude the Arbitral

Tribunal from taking another related contract into

consideration. There is a distinction between giving

effect to another contract by deciding issues under it

and taking that contract into consideration for the

purposes of interpretation and application of the

agreements falling within the jurisdiction of the

Arbitral Tribunal. Therefore, there would be no lack of

jurisdiction to consider the nature of the agreement of

the appellant with the respondent No.2 in context of

three Agreements with the respondent No.1 for a

comprehensive understanding of the nature of the

transaction. Such consideration may become necessary to

ascertain the intention of the parties as to whether they

conceived of various agreements as forming together one

single economic transaction. The Court can, therefore,

always take into consideration the related contracts to

ascertain the nature of the transaction while deciding

the question of interim measures under section 9,

because, a truncated view of the transaction cannot guide

the Court as to what interim measures are required. That

would not amount to enforcing any liability under any

contract for which the Arbitral Tribunal may have no

jurisdiction.

11. Proceeding on the footing that a Court can issue

orders of interim measures of protection as contemplated

by the provision of section 9 of the said Act on the

above reasoning, it would have to be now seen whether

there is a case made out by the appellant for a mandatory

order against the respondent No.2 subject to whose

control its wholly owned subsidiary, the respondent No.1,

which was created for the purpose of the contract in

India (which appears to be the case from the letter of

November 13, 1999, Volume II Page 1 of the appellant's

paperbook, written by the respondent No.2 - Lentges to

the appellant in which the last sentence reads: "Our

recommendation is to sign the outstanding contracts after

foundation of our company in India"). The respondent

No.2 and its subsidiary, the respondent No.1, had entered

into the agreements forming a consortium as can be seen

from the letter dated 11th July 1997 of the respondent

No.2 to the appellant (Annexure I collectively, Volume I

of the Appellant's Paperbook, on page 196-197). The

relevant portion of that letter, reads as follows :-

"Lentjes and the companies A, B, C shall form a

consortium and have a very clear legal agreement

overseen by Lentjes, controlled by Lentjes and

operated by Lentjes. It will be a separate

office at Bombay, team of personnel and

infrastructure for this specific job."

12. Under the "Know-how supervision agreement" dated

1st September 1997 between the appellant and the

respondent No.2, the respondent No.2 agreed that, "It

will undertake to supervise Engineering / Procurement,

Fabrication, Supply of Erection to be undertaken in a

manner that the boilers meet the guarantees stipulated in

this agreement as if the supply, erection and

commissioning has been done by Lentges (i.e. the

respondent No.2) itself and shall guarantee their

performance", as declared in clause (e) of the Preamble

of the Agreement. The respondent No.2 undertook full

responsibility for the workmanship of the Erection

contractor, Engineer, and Engineering supply contractor

as stipulated in para 1.6, 1.8 and 1.11 of its agreement.

The respondent No.2 undertook in clause 2.1(c) of the

agreement that, "Boilers once assembled, erected and

commissioned will operate in conformity of this agreement

as well as other agreements as may be entered by NIRMA

with Engineer, Contractor & Erection Contractor." The

Contractor / Engineer / Erection Contractor were to be

appointed as per the approval of the respondent No.2 and

the terms and conditions of contract with them (excepting

the commercial and financial terms) were to be previously

approved in writing by the respondent No.2 and then not

to be altered or amended without its previous approval.

This was actually done, because, in each of the three

agreements with the respondent No.1, it was mentioned

that the terms thereof were approved by the respondent

No.2. The respondent No.2 was to depute a Project

Manager to supervise all the stages upto the erection and

commissioning of the plant, as stated in Article VI(1) of

the agreement. The respondent No.2, in Article VII of

the agreement, gave guarantees to the appellant in the

following terms :

"ARTICLE VII : WARRANTIES :

7.1 LENTJES guarantees to NIRMA :-

(a) that the CONTRACTOR, ENGINEER and

ERECTION CONTRACTOR shall duly and timely

perform their respective obligations with

NIRMA as may be provided in their

respective contracts.

(b) the fulfillment of the warranties

contained in the respective contracts

with the CONTRACTOR, ENGINEER and

ERECTION CONTRACTOR.

(c) LENTJES shall be the principal guarantor

for due performance of the CFB boilers as

covered in this agreement and the said

guarantee shall be in addition to ay

guarantee(s) which NIRMA may have from

the CONTRACTOR, ENGINEER and ERECTION

CONTRACTOR. For due fulfillment of

guarantee obligation of LENTJES under

this clause, if need be, NIRMA agrees to

assign guarantee(s) of CONTRACTOR,

ENGINEER and ERECTION CONTRACTOR in

favour of LENTJES.

7.2 LENTJES agrees as principal guarantor to

accept the guarantee obligation as

mentioned in Annexure 6 of this agreement

and also agrees to monetarily or

otherwise compensate NIRMA for all the

obligations covered herein.

7.3 LENTJES' liability under this Article VII

shall, however, not exceed the

liabilities and the respective

liabilities of the ENGINEER, the

CONTRACTOR and / or the ERECTION

CONTRACTOR under this agreement and also

under their respective contracts with

NIRMA."

12.1 The above clauses of the agreement show that the

respondent No.2 had guaranteed, as a principal guarantor,

the due performance of CFB boilers and the obligations

under the respective contracts of the Contractor,

Engineer and Erection Contractor, with the appellant.

The respondent No.2 agreed to compensate the appellant

for all obligations of the Contractor, Engineer and

Erection Contractor under their respective contracts to

the extent of their liabilities. Thus, the respondent

No.2 stood as a guarantor to the appellant for due

performance of the obligations of the respondent No.1

towards the appellant under its three agreements on the

basis of which the arbitration disputes have been

referred to the Domestic Arbitral Tribunal.

12.2 The guarantee obligations mentioned in Appendix

VI of the agreement with the respondent No.2 were in

terms undertaken by the respondent No.2 under Article 7.2

of the agreement. As per these guarantee obligations,

the respondent No.2 had guaranteed "execution of the

order with good workmanship according to the technical

specifications and performance requirements, as handed

over to him". The guarantee period "started with the day

of preliminary passing of title and risk, after

successful completion of test operation", and was for

"10000 operating hours with in a max of 2 years", as per

the guarantee stipulation. If the respondent No.2 did

not comply with the performance guarantees even after

repairs and replacement, the appellant was entitled to

the liquidated damages per boiler unit (percentage of

contract price per boiler unit), as stipulated in the

guarantee obligations under the agreement of the

respondent No.2 (See page 347 of Volume I of the

appellant's paperbook in its Appendix VI).

12.3 Apart from the guarantee rights, the appellant

had a right not to accept the unit or part thereof in the

events enumerated in the guarantee obligations, which

included event of liquidated damages exceeding 10% of the

contract price. The agreement with the respondent No.2

was to be governed according to the laws of India, as

stipulated by Article 16.2 and 16.4. By clause 5 of

Article 16, it was agreed between the respondent No.2 and

the appellant that the appellant "shall have no claim or

demands against LENTJES (i.e. the respondent No.2) other

than those specified in the Agreement", and that the

liabilities of LENTJES to the appellant "shall be limited

to what is provided in the agreement and shall in the

aggregate be limited to 15% of the total order value

..... under this Agreement" as well as "15% of the total

order value of the agreements to be entered with the

Engineer, Contractor and Erection Contractor and such

limitation shall not be alterable by decision of

arbitration or court".

12.4 From the agreement executed by the respondent

No.2, it appears that the respondent No.2 had guaranteed

successful execution of the Work Order retaining its

complete control at all stages of the work to be done

through the respondent No.1 on the terms of the three

agreements executed by the respondent No.1, which was

wholly owned subsidiary of the respondent No.2 specially

founded in India for executing the Work Order,

obligations under which were guaranteed in no uncertain

terms by the respondent No.2. All the four agreements

read together spell out a pattern showing the dominance

of the respondent No.2 who undertook the successful

execution of all the agreements. It would be difficult

for such a principal guarantor to say that he is a

stranger to the three agreements entered into by its

wholly owned subsidiary in furtherance of the main

contract that it entered with the appellant to provide

three Boilers to the appellant.

13. However, the fact remains that the arbitration

clause contained in Article 15 of the agreement with the

respondent No.2 stipulated that if at any time any

question / dispute or difference whatsoever shall arise

between the respondent No.2 and the appellant out of or

in connection with this Agreement, the same shall be

finally settled by arbitration in accordance with the

Rules of Conciliation and Arbitration of the

International Chamber of Commerce. The place of

arbitration shall be London and arbitration proceedings

shall be carried out in England. On the strength of this

clause, the respondent No.2 has taken up a stand that the

Domestic Arbitral Tribunal will have no jurisdiction over

the respondent No.2 and therefore, the interim relief

cannot be issued either by the Arbitral Tribunal or by

the Court under sections 9 and 17 of the Act, even if the

respondent No.2 was to be treated as a guarantor for the

obligations of the respondent No.1 under the three

agreements including the obligation to conduct the

performance tests.

13.1 It was urged in the above background, on behalf

of the appellant that, having regard to the nature of the

transaction, the Court will have power to issue interim

relief even against the respondent No.2 though not a

party to the arbitration proceeding, as on today, and

therefore, the respondent No.2 can be compelled to do

performance test on the three boilers in order to

demonstrate "that the boiler is capable of operating in

accordance with the technical specifications", as was

stipulated by the respondent No.2 under Article 8.2.1 of

the contract. It was argued that the respondent No.1 was

only a "shell" company founded by the respondent No.2 for

the purpose of the contract and the respondent No.1 had

no means to satisfy the claim of the appellant and

therefore, the respondent No.2 should also be asked to

furnish a bank guarantee in the sum claimed by the

appellant who was entitled to get back the entire amount

paid under the contracts from the respondents Nos. 1 and

2, as per the Statement of Claim.

13.2 The respondent No.2 had moved the Tribunal for

holding that it had no jurisdiction over the respondent

No.2 in view of the arbitration clause in Article 15 of

the Agreement, which stipulated that the seat of

arbitration will be at London. This order was confirmed

by the Court in Appeal and a Revision Application is

pending with the High Court, as noted above. Therefore,

as on today, the respondent No.2 is held to be not

amenable to the jurisdiction of the Arbitral tribunal

since it was not a signatory to the arbitral clause

contained in any of the three agreements with the

respondent No.1. However, that aspect is quite distinct

from the power of the court to grant interim measures

under section 9 of the Act, which may extend even against

the third party. These powers are same as those

exercisale for the purpose of and in relation to any

proceeding before it. A surety will not be a stranger to

contract of guarantee since it is a triparte contract

which makes the liability of a surety co-extensive with

that of the principal debtor, though indeed a separate

liability. In contrast to section 17 under which the

interim measures that can be issued by the Arbitral

Tribunal only against the parties to the arbitration

agreement, the Court can in a given case issue interim

measures against the parties not involved in the

arbitration and such measures would be enforceable

through the local judicial system, (See paragraph 4.038

at page 120 of "International Commercial Arbitration in

UNCITRAL Model Law Jurisdiction" by Dr.Peter Binder,

First Edition (2000) published by Sweet & Maxwell). The

applications under section 9 to Court will be appropriate

where the order is sought against the third party over

whom the Tribunal had no jurisdiction or where any order

by the Tribunal is likely to be ineffective. (See para

5.096 at page 205 of Russel on Arbitration, 21st

Edition).

13.3 The Supreme Court in Sundaram Finance Ltd.

(supra) has held that, for construing the provisions of

the said Act, it is more relevant to refer the UNCITRAL

Model Law rather than the Act of 1940. In context of the

powers of the Arbitral Tribunal under section 17 and of

the Court under section 9, it observed in paragraph 11 of

the judgement that, though section 17 gives the Arbitral

Tribunal power to pass orders, the same cannot be

enforced as orders of a Court. It is for this reason

that section 9 gives the Court power to pass interim

orders during arbitration proceedings. It was held that

reading the provisions of section 9 as a whole, it

appears that the Court has jurisdiction to entertain an

application under section 9 either before arbitral

proceedings or during the arbitral proceedings or after

making of the arbitral award but before it is enforced in

accordance with section 36 of the Act.

13.4 In Bhatia International (supra), the Supreme

Court has held that an application for interim measure

can be made to Courts in India, whether or not the

arbitration takes place in India before or during the

arbitral proceedings (see paragraph 28 of the judgement).

It was held that the provisions of Part I of the Act

would apply to all arbitrations and to all proceedings

relating thereto. Where such arbitration is held in

India, the provisions of Part I would compulsorily apply

and the parties are free to deviate only to the extent

permitted by the derogative provision of Part I. In case

of international commercial arbitrations, held out of

India, provisions of Part I would apply unless the

parties by agreement express or implied, exclude all or

any of the provisions. In that case, laws or rules

chosen by the parties would prevail. Any provision in

Part I, which is contrary or excluded by that law or

rules, will not apply.

13.5 In the present case, under Articles 16.2 and 16.4

of the agreement between the appellant and the respondent

No.2, the agreement was to be governed according to the

laws of India which will include the said Act. The

provisions of section 9 of the said Act are not excluded

under that agreement. This Court will, therefore, have

powers under section 9 of the said Act to issue interim

injunction against the respondent No.2 even if

arbitration proceedings on the basis of that agreement

are pending before the ICC, London, while the arbitration

proceedings on the basis of the three agreements of its

subsidiary, the respondent No.1, in respect of which the

obligations have been guaranteed by the respondent No.2

under the contract is pending in the Arbitral Tribunal,

at Ahmedabad.

14. We may therefore now examine whether any case is

made out by the appellant for grant of any interim relief

under section 9 of the said Act against the respondents.

In paragraph 69 of the application made under section 9

of the said Act before the Court, the appellant seeks,

"an appropriate order of interim measure of protection

against the respondents directing them to preserve

boilers Nos. 1, 2 and 3 contracted to be supplied by

them under agreements dated 12-12-97, 12-12-97 and

17-3-98 at the petitioner's plant in Bhavnagar by

conducting the "Start-Up" and "Performance Test Run" and

further achieve the agreed parameters as per Annexure VI

of the contract dated 1-9-1997 between the petitioner and

respondent No.2 till the hearing and final disposal of

the main petition".

14.1 According to the appellant, it has a prima facie

case and balance of convenience is in its favour, and

that if the interim reliefs are not granted, the

appellant will suffer irreparable loss and injury "which

can never be assessed or compensated in terms of money".

14.2 The contract of supply of boilers in respect of

which the respondent No.2 had intellectual property

rights was not a contract to buy goods freely available

across the counter. The nature of the four agreements

and the details given in the Annexures to the agreement

dated 1-9-1997 between the appellant and the respondent

No.2 would show that these Boilers were unique goods, the

installation and operation of which was possible only

with the special know-how of the respondent No.2. This

is why it has been argued by the learned Senior Counsel

appearing for the appellant that the essential part of

the contract, namely, of conducting "Performance Test

Run", which admittedly was not conducted by the

respondents as stipulated in the contract, should be

ordered to be performed with a view to preserve these

three boilers since the special know-how was available

only with the respondent No.2 and the appellant was under

an obligation not to disclose any secrets of the design

and operation of the boilers to any outside agency for

getting the performance test conducted. It was argued

that until such test was done, there was no legal

entrustment of the boilers to the appellant and the risk

remained with the respondents who continued to be bound

under the contract to preserve these boilers. It was

argued that the performance guarantee period of two years

or 10000 operative hours would run only after the

performance test was conducted by the respondents.

Relying on the provisions of section 23 of the specific

Relief Act, the learned Senior Counsel argued that the

liquidation of damages was by itself not a bar to

specific performance in the present case.

14.3 The specific performance of a contract can be

enforced when there exists no standard for ascertaining

the actual damage caused by the non-performance of the

act agreed to be done or when the act agreed to be done

is such that compensation in money for its

non-performance would not afford an adequate relief. In

case of contract of transfer of movable property which is

not an article of commerce, or is of special value or

interest to the plaintiff, or consists of goods which are

not easily obtainable in the market, there would be a

presumption by the Court that the breach of such contract

cannot be adequately relieved by compensation in money.

This is borne out from the provisions of section 10 of

the Specific Relief Act. Such presumption would,

however, be a rebuttable presumption. Section 23 of the

Specific Relief Act, provides that liquidation of damages

named in the contract is not a bar to specific

performance, if such contract is otherwise proper to be

specifically enforced. Therefore, if a contract is of

the type which cannot be specifically enforced, the

provisions of section 23 cannot be pressed into service.

In a contract for building or engineering works since a

Court has no means of supervising, it will not usually

grant remedy of specific performance. Moreover, remedy

of specific performance has to be sought by the plaintiff

to enable the Court to consider whether it may be

granted. If the plaintiff does not, as in the instant

case, pray for specific performance, but instead claims

damages for breach of contract, the plaintiff disentitles

itself, on account of his own election to treat the

contract as breached, from claiming specific performance

of the same contract. The appellant has admittedly not

prayed for specific performance of the terms of contract

under which the respondent No.2 was expected to conduct

the performance test run. This is evident from the

prayer clauses 73(A) and (B) of the Statement of Claim

dated 12-11-2000 filed by the appellant before the

Arbitral Tribunal (a copy of which is at Volume III of

the appellant's paperbook, Annexure ZE, page 255 to 297),

in which a declaration is sought that, "the respondent

No.1 has failed to perform its obligations under the

Agreements dated 12-12-1997, 12-12-1997 and 17-3-1998",

and repayment of Rs.60,67,18,000=00 is claimed from the

first respondent on account of its failure to perform its

obligations". It was prayed in clause (m) that the

"declarations as prayed for above be directed to be

passed against the respondents 1 and 2 jointly and

severally."

14.4 In none of the prayers made by the appellant in

the Statement of Claim before the Arbitral Tribunal, did

the appellant claim specific performance of any part of

the contract. There was no request made for any

direction on the respondents to conduct performance test.

The claim of the appellant was on the footing that there

was a breach of contract committed by the respondents and

it was made "on account of failure on the part of the

respondents to supply boilers of agreed parameters" (See

para 68(1) of the Statement of Claim). Since the

appellant did not pray for specific performance of the

terms of contract which required the respondents to

conduct performance test run, but claimed for a

declaration of breach of contract and repayment of

amounts paid to the respondent No.1 and made other money

claims for damages for breach of contract, the appellant

disentitled itself, on account of its own election of the

remedy of claiming compensation for breach allegedly

committed by the respondents, to claim specific

performance. The appellant did not even claim, "specific

performance with compensation". Therefore, the prayer in

the application under section 9 claiming specific

performance of the terms of contract requiring

performance test run to be conducted by the respondents

is not at all warranted and cannot be granted as an

interim measure of protection.

15. That takes us to the alternative prayer in para

69(b) of the application, in which the appellant seeks an

interim measure of protection directing the respondents

to deposit a sum of Rs.6,53,00,000=00 to be released to

the appellant so as to enable the appellant "to conduct

the Start-Up and Performance Test Run by engaging any

other agency, as may be deemed appropriate" by the

appellant till the final disposal of the petition. A

direction is also sought in para 69(d) on the respondents

to secure by way of a bank guarantee a sum of

Rs.60,67,18,000=00 paid by the appellant, subject to the

award that may be passed by the Arbitration Tribunal.

15.1 The learned Senior Counsel for the appellant, in

support of these prayers submitted that the appellant was

entitled to reject the boiler units and claim the entire

amount paid, because, the boilers were not as per the

parameters agreed. He argued that since the appellant

cannot be expected to bring the entire Soda Ash Plant to

a standstill, it was as per the Contract entitled to

continue to use these boilers, till it could procure

"suitable replacement" as contemplated by the terms of

guarantee obligations mentioned in Appendix VI of the

contract dated 1-9-1997 executed by the respondent No.2.

He also submitted that since the respondent No.1 was only

a "shell" company, wholly owned by the respondent No.2 in

order to ensure that the award that may be made in favour

of the appellant may not be frustrated, the respondents

should be ordered to furnish security as prayed for in

the application.

15.2 There is no dispute over the fact that the

Appellant has not paid the last 10% of the total

consideration, being the final amount payable under the

contracts on "completion of Performance Test Run" as

contemplated by all the agreements. There is also no

dispute over the fact that the Performance Test Run was

not conducted; but the rival parties have blamed each

other for the test not being conducted.

15.3 We have been taken through a mass of documentary

evidence with a fervour of original side advocacy by the

learned counsel appearing for both the sides in their tug

of war to show the respective strength of their cases for

and against the grant of an interim relief. The fact

that emerges without much dispute is that the appellant

has not till now rejected any of the boilers and has been

in fact using them for its Soda Ash Plant after being

handed over the boilers, and that it has not paid the

final payment of 10% of the total consideration under any

of the contracts which was payable against performance

bank guarantee as well as on completion of the

performance test run and further that the appellant

invoked the bank guarantee of Rs.13 crores which were

advanced to the respondent No.1 due to "the default in

commissioning the three boilers in accordance with the

agreed schedule", as stated in para 6 of the appellant's

letter dated July 29, 2000 addressed to the respondent

No.1 (Copy at Annexure ZB in Volume II of the appellant's

paperbook at page 241 - 246).

15.4 Certificate of mechanical completion was to be

given in respect of each boiler in respect of which

positive result was achieved at the conclusion of the

mechanical completion, as contemplated by Article 7.10.3

of the Agreement for Erection and Commissioning,

reproduced hereunder :

"7.10.3 If at the conclusion of Mechanical

Completion test of each Boiler, positive

result is achieved, then in that event

ERECTION CONTRACTOR shall prepare and

NIRMA shall sign the Provisional

Acceptance Certificate for that Boiler.

The issue of Acceptance Certificate shall

not absolve ERECTION CONTRACTOR from

rectifying minor or unsubstantial defects

in the boiler.

7.10.4 In case a successful Mechanical

Completion Test should not be possible

due to reasons not attributable to

ERECTION CONTRACTOR within 7 months after

the Mechanical Completion date, or such

extended time as agreed upon between the

parties, such boiler shall be considered

as accepted and a Provisional Acceptance

Certificate shall be issued by NIRMA.

7.10.5 During the Mechanical Completion Test if

it is observed that some minor

rectifications are required or

unsubstantial defects are noticed,

ERECTION CONTRACTOR shall rectify the

same as its own cost."

15.5 The expression "Mechanical Completion" and

"Mechanical Completion Certificate" are defined in

Articles 1.8 and 1.9 as follows :

"1.8 "Mechanical Completion" shall mean that

an individual boiler has been completed

in all respect to enable preparation for

start up under normal conditions without

danger to the personnel and equipment

according to the provisions of Article 7.

1.9 "Mechanical Completion Certificate" shall

mean certificate certifying that all

items required for normal operation of an

individual boiler has been duly

assembled, erected and commissioned in

accordance with the technical

specification."

15.6 Admittedly, "Mechanical Completion Certificate

and Provisional Acceptance Certificate" were issued in

respect of all the three boilers by the appellant subject

to the "punch list" attached to them (See Annexure ZE of

Volume III of the appellant's paperbook on pages

255-297).

15.7 The performance test run was to be conducted as

contemplated by clause 7.12 of the Agreement for Erection

and Commissioning to find out whether at the conclusion

of such test, the guarantee performance as setout in the

contract with the respondent No.2 was achieved for the

boiler. If it was so achieved, the appellant was

required to sign the performance acceptance certificate

for that boiler, as per clause 7.12.2, reproduced below :

"7.12.2 At the conclusion of performance test of

each Boiler, the guaranteed performance

as set out in CONTRACT hereto are

achieved for that Boiler then in that

event ERECTION CONTRACTOR shall prepare

and NIRMA shall sign the Performance

Acceptance Certificate for that Boiler.

Such certificate shall state that

ERECTION CONTRACTOR has duly fulfilled

its contractual obligations and is

discharged therefrom in respect of that

boiler. The issue of Acceptance

Certificate shall not absolve ERECTION

CONTRACTOR from rectifying minor or

unsubstantial defects in the boiler."

15.8 The performance bank guarantee given by the

respondent No.1 could be encashed if parameters of the

performance test were not achieved because of defective /

poor workmanship. However, the maximum liability on

account of non-performance was stipulated to be 10% of

the order value as agreed under Article 7.12.3 of the

Agreement for Erection and Commissioning, and clause 4(b)

of the specific conditions of Work Order annexed thereto,

which read as under :

"7.12.3 As per the CONTRACT, parameters of the

performance test are to be achieved.

Because of defective/poor workmanship

delivered by the ERECTION CONTRACTOR,

performance parameters negatively deviate

from the guaranteed figure, ERECTION

CONTRACTOR shall be liable for liquidated

damages and, NIRMA shall be free to

encash the Performance Bank Guarantee to

be received from the ERECTION CONTRACTOR,

without any further reference/recourse to

the ERECTION CONTRACTOR, and other

suitable action as may be required to be

taken by NIRMA under the Agreement as

well as the CONTRACT. However, the

maximum liability on account of

non-performance shall be 10% of the Order

Value."

"4(b). FOR NON PERFORMANCE:

The 3 nos. of CFB Boilers of 100 tph

each after their erection and

commissioning shall perform as per the

guarantee parameters. Because of the

defective poor workmanship delivered by

LENTJES ENERGY (INDIA) LTD. performance

parameters negatively deviate from the

guaranteed figure, you shall be liable

for liquidated damages and Nirma shall be

free to encash the Performance Bank

Guarantee to be received from you without

any further recourse to you. However the

maximum liability of non-performance

shall be 10% of the total order value."

Thus, a ceiling of liability was fixed for

failure of performance test run at 10% of the total order

value.

15.9 Admittedly, since no performance test was carried

out for the blames attributed by the parties to each

other, final payment of 10% of consideration stipulated

in the terms of payment in all the agreements to be paid

against a performance bank guarantee and completion of

performance test and certificate issued by the appellant,

was in fact not paid, and on that count, the appellant,

therefore, has withheld final payment of 10% of the

entire consideration payable under all the agreements.

(See Article 3.2.3, 3.2.6 and 3.2.10 of the contract

executed by the respondent No.2, and Article 4.4.8 of the

Engineering Contract, Article 3.5.9 of the Supply

Contract and Article 4.4.4 of the Erection and

Commissioning Contract).

16. Apart from withholding 10% of the total

consideration due to the respondent No.2 not conducting

the performance test, the appellant had invoked the

performance bank guarantee which was stipulated in

Article 4.4.4 of the Agreement for Erection and

Commissioning. The appellant had by letter dated

28-7-2000 (at Annexure ZA in Volume II of the appellant's

paperbook on page 240) invoked the bank guarantee dated

22-9-1999 for a sum of Rs.13 crores. In paragraphs 6 and

7, reproduced below, of its letter dated 29-7-2000

(Annexure ZB of the said Volume II) addressed to the

respondent No.1, the appellant informed the respondent

No.1 that it had invoked the bank guarantee owing to

"defaults and a history of failure".

"6. You had repeatedly requested us to bail

you out of your purported financial

difficulties. Pursuant to such request,

with a view to maintain a cordial

business relationship, we agreed to

advance you a sum of Rs.

13,00,00,000/(Rupees thirteen crores

only) contingent on your promise that you

would meet the revised schedule for full

and formal commissioning of the three

boilers. In order to secure the

aforesaid advance of Rs. 13 crores, you

had executed an irrevocable and

unconditional bank guarantee for the said

sum of Rs. 13 crores. It was also

mutually agreed between us in the event

of any failure, or default in

commissioning the three boilers in

accordance with our agreed schedules,

Nirma would be free to invoke the bank

guarantee and take back the said advance

of Rs. 13 crores.

7. This is to inform you that owing to

repeated defaults and a chronic history

of failure in meeting contracted

deadline, Nirma has now been constrained

to invoke the aforesaid bank guarantee in

order to protect its interests of its

shareholders."

16.1 The above guarantee, a copy of which was mutually

made available by the learned counsel to the Court on

inquiring about it during the arguments, referred to the

fact that the respondents Nos. 1 and 2 were required

under the boiler agreement to provide the appellant "with

performance guarantees for the performance of all the

three CFB Boilers, after each of the three boilers is

installed and commissioned". It also mentions; "The

value of performance guarantees of Lentjes India

amounting to Rs.65,332,356/- [Rupees sixty five million

three hundred thirty two thousand three hundred fifty six

only], for these three CFB Boilers is included in this

value of Bank Guarantee of Rs.130,000,000/- [Rupees one

hundred and thirty million only]". It further records

that, "Lentjes (i.e. the respondent No.2) has requested

the Bank to provide the Bank Guarantee as required, and

the Bank has agreed to do so ......". The relevant

covenant showing that the guarantee was in respect of the

performance guarantees of both the respondents Nos. 1

and 2 contained in the said deed reads as follows :

"AND THE BANK DOES FURTHER COVENANT AND DECLARE

that this Guarantee is absolute, unconditional

and irrevocable and shall remain in force upto

31.03.2000 or upto and inclusive of the date on

which Lentjes and Lentjes India execute all the

Performance Guarantees in favour of Nirma as

required of them in terms of their respective

agreements with Nirma, whichever is earlier. The

Bank shall be discharged from its liabilities

arising out of this Deed of Guarantee only when

Nirma or Lentjes or Lentjes India submits to the

Bank Performance Guarantee Certificates signed by

Nirma's duly authorised official confirming

successful completion of Performance Test as per

the Performance Guarantee Parameters provided in

the Boiler Agreements and receipt of the said

Performance Guarantees. If Nirma is not able to

submit to the Bank both these Certificates before

31.03.2000, then this Bank Guarantee shall

automatically be renewed on the same terms and

conditions for a period upto 31.12.2000."

16.3 When the said bank guarantee was invoked by the

appellant, the effect was that the appellant received

thirteen crores of rupees from the bank since performance

test run was not done and consequential performance

guarantee certificate which would have been issued by the

appellant, had the test been duly conducted with positive

result, could not be submitted by the respondent No.1 to

the bank for the discharge of the bank's liability. This

amount of Rs.13 crores included the value of the

performance guarantees of the respondent No.1 amounting

to Rs.65,332,356/- as stated in the deed of guarantee.

Over and above getting the amount of Rs.13 crores by

invoking the bank guarantee which included the value of

the performance guarantees of the respondent No.1, the

appellant also had admittedly withheld 10% of the total

consideration payable under the agreements as final

payment against the performance bank guarantees and the

performance test run.

17. Thus, in sum, the result is that -

[a] The appellant is in possession of the three

boilers in respect of which it had issued

mechanical completion and provisional acceptance

certificates.

[b] These boilers are admittedly being put to actual

commercial use by the appellant.

[c] The final payment amount which was 10% of the

total consideration i.e. Rs.6.53 crores was

withheld by the appellant since the performance

test against which the said final payment was to

be made, was not conducted.

[d] The appellant has already invoked the performance

bank guarantee of Rs.13 crores on the ground that

the performance test was not done and the boilers

were faulty.

18. On the above facts, we are of the opinion that no

further security is called for by issuing any interim

measure under section 9 of the Act, and that the

appellant has already taken steps to substantially

safeguard its own interest. Having regard to the

aggregate ceiling of all damages stipulated between the

parties in para 11.4 of the agreement also, there is no

need for any interim measure to be ordered by the Court

under section 9 of the Act. Denial of interim relief by

the trial Court was, therefore, perfectly justified in

the facts of the case. The appeal is, therefore,

dismissed with costs.

[R.K.ABICHANDANI, J.]

[M.C.PATEL, J.]

parmar*



Top